Public Meeting, October 25,
2006
Citizens & Project Team Discuss
Preliminary Design, Cost Estimate
& Financing Strategies
On Wednesday, October 25,
2006, Jefferson County hosted
a public meeting at the WSU
Extension to provide information
and take public
comment on a sewer study
being conducted in the Irondale/Port
Hadlock area. The goal of the
sewer study is to prepare a
comprehensive sewer facility
plan that will help the County
plan for growth in the Irondale/Port
Hadlock area through the year
2030. Approximately 50 members
of the community attended the
public meeting.
During an informal open house period from 5:30 p.m. to 6:00 p.m., there were large boards posted around the room with information about the sewer planning process, the preferred sewer system alternative, and potential locations for wastewater facilities. Public meeting attendees were encouraged to view the information and talk with members of the project team.
The consultant team that the
County hired to conduct the
Irondale/Port Hadlock sewer
study gave a presentation and
responded to questions about
the cost estimate, potential
financing strategies, and progress
on preliminary design for the
preferred sewer system alternative.
The consultant team described
next steps in the decision-making
process and opportunities for
public involvement. Members
of the consultant team included
project manager Kevin Dour,
TetraTech/KCM; Jim Santroch,
TetraTech/KCM; Katy Isaksen,
Katy Isaksen and Associates;
and Bob Wheeler, Triangle Associates.
The PowerPoint
presentation is attached.
Mr. Wheeler said that having a sewer facility plan approved by the Department of Ecology would make the sewer project eligible for a variety of state and federal funding programs. Ms. Isaksen explained that while developing realistic cost estimates and financing strategies was a required component of the sewer facility plan, it was also important as a way to identify the best financing sources available to launch the sewer system. She said that the consultant team had used conservative assumptions to develop the cost estimates to make sure that the project could be done within the estimated budgets.
During the meeting, many questions
from the public related
to the decision-making process
for the sewer, the results of
preliminary design, and the
cost estimate and financing
strategies. The consultant team,
County staff, and County Commissioner
David Sullivan (District 2)
provided responses based on
available information.
Ms. Isaksen emphasized that more work would be done during the implementation phase, after the sewer facility plan was approved, to reduce project costs, secure funding assistance, and finalize the method of distributing costs. Mr. Wheeler reviewed the schedule for completing the sewer facility plan and noted that another public meeting would be scheduled before the plan was finalized.
Public
Meeting, July 19, 2006
Citizens & Project Team
Discuss Recommended Sewer System
Alternative
On Wednesday, July 19, 2006,
Jefferson County hosted a public
meeting at the Jefferson County
Library to provide information
and take public
comment on a sewer study
being conducted in the Irondale/Port
Hadlock area. The goal of the
sewer study is to prepare a
comprehensive sewer facility
plan that will help the County
plan for growth in the Irondale/Port
Hadlock area through the year
2030. Approximately 50 members
of the community attended the
public meeting.
During an informal open house
period from 5:00 p.m. to 6:15
p.m., information was posted
on large boards about the sewer
planning process, the sewer
system alternatives that were
considered, potential locations
for wastewater facilities, and
preliminary cost estimates.
Public meeting attendees were
encouraged to view the information
and talk with members of the
project team.
Kevin Dour and Jim Santroch
of TetraTech/KCM, the consultant
team hired by the County to
conduct the sewer study, presented
and responded to questions about
the alternatives for the sewer
system and the rationale, from
a technical standpoint, for
the recommended alternative.
The consultant described next
steps in the decision-making
process and opportunities for
public involvement.
Many questions
from the public related
to the cost of a sewer system,
how effluent disposal/reuse
would affect groundwater, and
where wastewater facilities
would be located. The consultant
provided responses based on
the preliminary information
that was available.
The consultant explained that
more detailed information about
siting, impacts on hydrology,
and cost estimates and financing
options would be developed after
the selection of a preferred
sewer system alternative. They
said the focus of the financing
options would be on community
affordability. They explained
that the Board of Jefferson
County Commissioners would review
the consultant team's technical
recommendation at an August
8 workshop and would then make
a decision on the preferred
alternative.
The consultant team's recommendation
is based on engineering feasibility,
responsiveness to community
concerns, compliance with regulatory
requirements, preliminary cost
estimates, and environmental
considerations.
To provide local input, public
workshops were held to advise
the sewer study process. Workshop
participants included County
Commissioners, local agency
representatives, community leaders,
and other interested parties.
Over the course of three workshops,
workshop participants and the
consultant team reviewed and
evaluated a comprehensive array
of sewer system alternatives.
The workshop participants identified
their preferences for each component
of the sewer system, including
wastewater collection, treatment,
effluent disinfection, effluent
disposal/reuse, and solids handling.
The consultant team used those
preferences to help develop
the technical recommendation
that was presented at the public
meeting. The workshops were
advertised in advance and were
open to the public.
|